Drive east on RM 2222 from River Place toward the city and the road ends at Loop 360. That is where the drive to work, school or errands turns north or south. The Texas Department of Transportation is now rebuilding that junction and the mile of Loop 360 south of it toward the Pennybacker Bridge. TxDOT's Courtyard Drive/RM 2222 project page gives the scope. The traffic signal on the Loop 360 mainlanes at Courtyard Drive comes out and an underpass goes in. RM 2222 at Loop 360 becomes a diverging diamond interchange. New shared-use paths and sidewalks run through the work zone.
TxDOT's April 2026 construction sheet lists the cost at $68.4 million, names Webber as the contractor and expects the work to take three to four years from its April 2026 start. The project page puts completion in late 2029.
For someone coming from River Place, the order of the work matters more than the end date. The interchange at RM 2222 is the third of four phases. It can't start until the Courtyard Drive bridge, a little to the south, is finished.
The Order TxDOT Set
TxDOT breaks the project into four phases.
- Phase 1. Set up the work zone, build waterlines and excavate the cliffs.
- Phase 2. Build new northbound and southbound connector roads, drainage, braided ramps and the Courtyard Drive bridge. Start the shared-use paths.
- Phase 3. Build the RM 2222 diverging diamond interchange and finish the shared-use paths.
- Phase 4. Do the final paving and striping, then open the permanent traffic patterns.
The Austin American-Statesman's May 2026 construction guide quoted TxDOT spokesperson Katherine Lee Seth on how the phases connect. In the guide's words, "Courtyard bridge construction will finish before work begins on phase three to build the diverging diamond at RM 2222."
In practice, the junction River Place drivers use most is the last piece of new road built before final paving. The first phase alone takes a while. KXAN reported in September 2026 that Phase 1 is expected to last until summer 2027.
The First Change at the River Place End Is Small
Most of the project is still ahead, but the RM 2222 end is already changing in small ways. TxDOT's project page lists overnight closures of the RM 2222 entrance ramp to southbound Loop 360 from 8 p.m. to 5 a.m. on the nights of Nov. 8 through Nov. 11. It also lists overnight alternating single-lane closures on Courtyard Drive at Loop 360.
The same page scheduled a new movement for drivers coming from River Place. A new eastbound RM 2222 right-turn lane to southbound Loop 360 was set to open as soon as the morning of Thursday, Nov. 12. TxDOT's instruction for using it:
"Drivers on eastbound RM 2222 will use the right lane and yield to westbound RM 2222 traffic."
That matters for a southbound trip toward Westlake or South Austin. A right turn that yields to oncoming westbound traffic works differently from a signal-controlled turn. Drivers who know that ahead of time have an easier first few mornings.
Lane closures and new turn lanes like this one are the visible part of a project that has years left to run. TxDOT updates the lane-closure list on the same project page.
Why the Cliffs Come First
Cliff work sets the pace for everything after it. Loop 360 between Courtyard Drive and RM 2222 runs through cut limestone. The new connector roads and ramps need room that the current road doesn't have.
TxDOT's April 2025 project FAQ says the cliff cuts vary in depth along the corridor. On both sides of Loop 360, the top of the new cut will sit at least 35 feet from the existing TxDOT right of way, and in some places more. The FAQ says the contractor and TxDOT decide together how to excavate, whether mechanically, by blasting or with a combination of the two.
The construction schedule shows how long and wide the work day is. Crews work weekdays from 7 a.m. to 7 p.m. and, when needed, Saturdays from 7 a.m. to 3 p.m. The same KXAN report covered residents of the Courtyard neighborhood, beside the highway, who described drilling, dust and vibration from work happening close to their homes. For someone passing through from River Place, that schedule explains why the work zone looks the same from one month to the next. Most of the early effort goes into moving rock.
What Phase 2 Takes Away Before Phase 3 Gives Anything Back
The Courtyard Drive bridge holds up everything after it, and building it changes one movement for several years. The Statesman reported that during Phase 2, drivers will lose the ability to cross Loop 360 at Courtyard Drive and will be rerouted along Loop 360. Work starts on the east side, next to the northbound lanes, and moves west.
The finished design also changes how one turn works for good. The FAQ explains that keeping the current turn from northbound Loop 360 onto eastbound Courtyard Drive would mean a sharp turn with barriers on both sides, because the Pennybacker Bridge is so close and Courtyard Drive climbs steeply. TxDOT added a northbound braided entrance ramp that reaches eastbound Courtyard Drive through the north neighborhood entrance.
How the Diverging Diamond Will Work at RM 2222
Once Phase 3 arrives, the intersection at the end of the drive from River Place will look different from any junction on RM 2222 today. TxDOT's diverging diamond fact sheet describes the movement. Traffic crosses to the left side of the road at signalized points. From there, drivers make a protected left turn or continue through and cross back to the right. Through traffic on Loop 360 can stay on the mainlanes or use a bypass lane.
| Movement from eastbound RM 2222 | What the finished design does |
|---|---|
| Left turn toward Loop 360 | Drivers cross to the left side at a signal and turn left without opposing traffic |
| Straight through the interchange | Drivers cross to the left side, then cross back to the right after the interchange |
| Through trips on Loop 360 | Mainlanes or a bypass lane carry through traffic past the junction |
TxDOT's reasoning, as the Statesman reported it, is that most traffic on Loop 360 is through traffic. Removing the signals and moving turning cars out of the mainlanes should keep that traffic flowing.
The Bridge Stays the Same, but Overlook Parking Changes
The Pennybacker Bridge isn't part of the project. The Statesman reported that the bridge, which has spanned the Colorado River since 1982, will remain two lanes in each direction. Getting to the overlook above it is a different story.
TxDOT's FAQ says the new road removes the shoulders where some drivers park to reach the Pennybacker Bridge overlook. In its May guide, the Statesman reported that crews setting up the work zone would install barriers near the overlook trail. Once they are in, cars can no longer park at the trailhead. The boat ramp near the bridge stays open.
The longer-term plan is a city one. On Dec. 12, 2024, the Austin City Council adopted a resolution to acquire land for a Loop 360 Overlook project. The resolution covers 1.110 acres in fee simple plus a 0.3648-acre easement for a sidewalk, trail and recreation. The posting listed the appraised value at $167,186. Community Impact reported that the purpose is public parking and an expanded trail at the overlook. TxDOT says it and the city are still working on a permanent solution.
Walking and Biking
The finished project includes shared-use paths and sidewalks. TxDOT starts them in Phase 2 and finishes them in Phase 3, alongside the diverging diamond. That means walking and biking along this stretch also has to wait for the final phases. The FAQ connects the paths to Federal Highway Administration guidance that federally funded projects include bicycle and pedestrian accommodations.
TxDOT's page lists utility contacts in case of questions during construction, though it doesn't expect service interruptions: AT&T at 800-288-2020, Austin Energy at 512-322-9100 and Texas Gas at 800-959-5325.
How long a commute takes is part of a home's value, and a multiyear project at the end of RM 2222 affects that for River Place households planning a sale, purchase or lease over the next few years. If you would like to talk through how the construction timeline fits your own plans, Thompson Real Estate Group invites you to initiate a private consultation.