The RM 620 widening got its first construction year this month. The stretch it covers runs from SH 71 to Dave Drive in Lakeway. The section past Steiner Ranch Boulevard and North Quinlan Park Road is a separate project on the regional plan, and it carries a target year of 2035.
Both entrances to Steiner Ranch meet RM 620 between Hudson Bend Road and RM 2222. On paper, that section of road is about six years behind the segment that was approved on October 5, 2026. Regional planners list the corridor as three separate projects lined up one after another. Each has its own ID number, its own cost estimate and its own year.
Three Projects Share One Road Name
The Capital Area Metropolitan Planning Organization, known as CAMPO, sets regional transportation priorities for the Austin area. Its 2050 Regional Transportation Plan was last amended on May 11, 2026. In that plan, the corridor from SH 71 north to RM 2222 appears as three line items, in this order:
- SH 71 to Aria Drive/Cavalier Drive, MPO ID 51-00199-00. The plan describes it as a widening from four lanes to a six-lane divided roadway, estimated at $73,024,000, with a 2033 year.
- Aria Drive/Cavalier Drive to Hudson Bend Road, MPO ID 51-00200-00. Same scope, estimated at $126,560,000, also with a 2033 year.
- RM 2222 to Hudson Bend Road, MPO ID 51-00204-00. This one widens four undivided lanes to six divided lanes. It is estimated at $204,093,322, with a 2035 year.
The third item is the one that runs past Steiner Ranch. It has the largest cost estimate of the three and the latest target year. It is also the only one described as starting from an undivided road. In other words, the stretch that carries Steiner Ranch traffic to and from RM 2222 starts from the most basic layout in the corridor and is scheduled last.
What the October 5 Vote Moved
Before the vote, the first project on that list changed shape. In September, Community Impact reported that part of the widening, from SH 71 to Dave Drive, had been proposed for CAMPO's 2027–2030 Transportation Improvement Program, with construction expected to begin at the start of fiscal year 2029. Unlike the long-range plan, the Transportation Improvement Program covers a near-term window of four years. It is adopted every two years and can be amended twice a year.
On October 5, 2026, CAMPO's Transportation Policy Board approved the amendments to both the improvement program and the regional plan by voice vote, as heard on the meeting recording. The approved list in the October 5 meeting packet includes RM 620 from SH 71 to Dave Drive, with the same ID, 51-00199-00. It is listed for construction in 2029, with an estimated cost of $151,200,878. The packet notes the project was previously listed in the 2025–2028 program.
The two documents use the same ID for different projects. The long-range plan shows 51-00199-00 ending at Aria Drive, costing about $73 million, with a 2033 year. The near-term program shows it ending at Dave Drive, costing about $151 million, with a 2029 year. The Lakeway segment got longer, roughly doubled in estimated cost, and moved up four years. Nothing in the October action changed the 2035 year on the segment past Steiner Ranch.
Lakeway's Objection Is About Where the First Segment Ends
Most of the public argument this fall has come from Lakeway, and it is mostly about the Lakeway end of the corridor. On September 8, Lakeway City Council passed a resolution formally asking CAMPO to extend project 51-00199-00 from Dave Drive through the city to Oak Grove Boulevard. The resolution also raised a concern that the expansion could end near Aria Drive. That would create a major change in the roadway near the entrance to Lake Travis High School, at one of the busiest intersections on that part of RM 620.
Community Impact quoted Lakeway Mayor Thomas Kilgore putting it directly: "No sane traffic engineer would have [RM] 620's expansion occur at the entrance of the high school." The city also has money in the project. According to the resolution, Lakeway paid the Texas Department of Transportation $3,222,096.70 in June 2023 to speed up the purchase of right-of-way.
The resolution also says the next project to the north, Aria Drive to Hudson Bend Road, has a 2033 target year "and no identified funding commitment." It points out that the first two segments appear to overlap between Aria Drive and Dave Drive. In the approved amendment list, the Lakeway project still ends at Dave Drive.
For Steiner Ranch, this sets the order of work. The fight in Lakeway is over how far the first segment reaches and how quickly the second one follows. The segment past Steiner Ranch comes after both, and the Hudson Bend Road end of the Steiner Ranch stretch only connects to a widened road once the middle segment is finished.
The Stretch Past Steiner Ranch Waits in the Long-Range Plan
Project 51-00204-00 covers RM 620 from RM 2222 to Hudson Bend Road. It includes the Steiner Ranch Boulevard and Quinlan Park Road intersections and the approach to Mansfield Dam. It sits in the 2050 Regional Transportation Plan with a 2035 year and two TxDOT control numbers, CSJ 0683-01-093 and CSJ 0683-02-067. In CAMPO's documents, that year is a planning target, and target years have already moved. The Lakeway segment's year went from 2033 in the long-range plan to 2029 in the near-term program within a single planning cycle.
Community Impact described the finished design for the full corridor from Hwy. 71 to RM 2222:
- Six through lanes
- Raised medians
- Right-turn and left-turn lanes at certain intersections
- A shared-use path on each side
Asked why the work is split up, CAMPO Community Outreach Manager Doise Miers told Community Impact that "Phasing construction projects into different segments is common and based on various factors." For the Steiner Ranch end, the medians and turn lanes at Steiner Ranch Boulevard and Quinlan Park Road arrive with the last phase.
What Has Already Changed Closer to Home
The county has done some smaller work at the neighborhood's edges. Travis County's capital improvement summary lists a preliminary engineering study of improvements at the Steiner Ranch Boulevard and RM 620 intersection as completed. That entry describes an engineering study, and the summary gives no completion date. The same summary lists a center turn lane on Quinlan Park Road, from Bella Mar Trail to Tierra Grande Trail, as completed.
The county also built the Steiner Ranch area's Evacuation Route B, which it lists as substantially complete on February 14, 2024. It is gated, closed to everyday traffic and controlled by first responders. That means it does not change the daily commute. For now, every trip that leaves through Steiner Ranch Boulevard or Quinlan Park Road still uses the four undivided lanes of RM 620 between Hudson Bend Road and RM 2222. Under the current plan, that stretch is scheduled to widen in 2035, six years after construction is set to begin on the Lakeway segment.
When a road project changes its schedule, it can affect how people think about a commute, an offer or a long hold on a property. If you want to talk through what the corridor schedule could mean for your plans, Ligaya and Bryan at Thompson Real Estate Group welcome you to initiate a private consultation.